Kate Spence writes:
The site plan below shows land to be assigned for
development by a partnering developer in Willesden Greeen as agreed by the
Executive Committee in February 2012. This plan was drawn up in order to define
the land made available in order to deliver a new Cultural Centre at zero cost.
The contracted developer, Galliford Try agreed to provide a new Centre
that would add cultural benefit to the area, the public realm was to be
enhanced and at the same time Council offices would be provided to provide a
South of Borough presence for Brent Council. In order to deliver the project at
zero cost, a master plan was agreed by Regeneration Team and the developer to
provide private housing to fund the project.
I note from Andy Bates' letter of 27th December
that, almost one year on, there is now further land required for disposal to
Galliford Try in order that proposed new Planning Application 12/2924 &
12/2925 can meet Planning Regulations. There has been no
question of the rear line of the Cultural Centre being adjusted to allow for
public provision as this would decrease the space available for private housing
and therefore reduce developer profit.
The developer has also not shown any willingness to reduce
profit and include a basement to house archive and museum allowing better
provision for public amenity. Instead it has been agreed, behind closed doors,
that yet more Public High Road, Conservation Area open space should be assigned
to Galliford Try for development purposes.
In the proposed plans the developer has failed to make space
for adequate on-site car parking provision, they are also unable to deliver
cycle parking. I can see that the proposed plans for Grange Road include
cycle parking and therefore a cycle route.
Currently the Grange Road area is enjoyed as a safe
pedestrianised walkway. Will the inclusion of a cycle route and parking enhance
this area and do the proposed children's pavement interventions really sit
safely alongside the cycle access? This appears to be yet another ill-conceived
plan which does not offer public benefit and will not enhance the area.
Has the post-contractual decision to give over yet further public land to achieve a large housing development with small Cultural Centre
been formally authorised by the Executive?
Clearly the allocated site was insufficient for the proposed
public facility along side the private housing and therefore yet more public
land has been assigned without consultation in order to achieve a positive
outcome for the applications ref 12/2924 and 12/ 2925.
The goal posts seem to have moved in order to facilitate an
untenable application and the basis on which the WGCC and housing contract was
signed with Galliford Try has been adjusted in order to make the unacceptable
plans viable. This alteration has been agreed by a Council who claim to be
impartial in their assessment of the scheme.
I do hope that when the scheme is presented to the Planning
Committee that there will be a more objective approach and the developers
requirement for additional public land in order to meet their objectives, will
be highlighted in the Planning officers report to the Committee.
I think that this is just another example of the mess that Galliford Try have got themselves into by signing up to Brent Regeneration Department's ill thought out scheme. I don't believe that Brent is planning to hand ownership of sections of public highway to the developer, but as the proposals involve work on areas that were not covered by the original site plan, they are having to put in an amended site plan to cover this mistake.
ReplyDeleteHowever, the revised site plan boundaries would probably allow the developer to put up fences right up to the new boundaries while development work is going on for a period of at least 18 months. How users of the west-bound bus stop in Brondesbury Park will be affected (has this been agreed with TfL?)and where pedestrians using the High Road, and trying to access the temporary library facilities in Grange Road, will be expected to go while these fences are in place has not been dealt with in the planning application (or if it has, I have not been able to find where it is dealt with).
These points, and others, will need to be made in comments under the resulting extra 21-day public consultation period, emphasising yet again what a terrible application this is, and why consent to it should be refused.
Philip Grant.
Hi,
ReplyDeleteGalliford Try have released a statement in response to the recent land acquisition claim that has appeared in the press.
See here for a full response - http://www.lindenhomes-consultation.co.uk/willesdengreencc
Many thanks,
The Project Team